GitHub - ByrCol/gantt-task-react: Gantt chart for React with Typescript

Interactive Gantt Chart for React with TypeScript.

A highly customizable and interactive Gantt chart component for React with TypeScript support. This repository integrates features and enhancements from the original MaTeMaTuK/gantt-task-react , the ObeoNetwork/gantt-task-react fork, and our current development, creating a comprehensive solution for managing Gantt charts.

multi-hierarchy.png

Key Features

  • Performance Improvements: Optimized rendering to handle large datasets efficiently, ensuring smooth user interactions.
  • Enhanced Customization: Allows for more extensive task styling options to match brand-specific requirements.
  • TypeScript Integration: Improved type definitions for safer and more efficient development workflows.
  • Responsive Design: Improved mobile and tablet support for better usability across different devices.
  • Dependency Management: Enhanced task dependency features, allowing for more complex project planning scenarios.
  • Advanced Timeline Navigation: Features smooth navigation across different timeframes like months and weeks.
  • Localization Support: Offers localization for various languages and date formats.
  • Event Handling: Supports comprehensive event handling for interactive features.
  • QuarterYear View Mode: Supports viewing tasks in quarterly segments, providing a flexible timeline view.

Enhancement Summary

This repository combines the foundational work of MaTeMaTuK/gantt-task-react with enhancements from ObeoNetwork, including better integration with TypeScript, improved rendering performance for large datasets, and new customization options for task styling. The project is further developed in this fork, focusing on additional usability improvements and feature expansions.

Installation

Install the package using npm:

npm install @wamra/gantt-task-react

How to use it

import { Gantt, Task, EventOption, StylingOption, ViewMode, DisplayOption } from '@wamra/gantt-task-react';
import "@wamra/gantt-task-react/dist/style.css";

let tasks: Task[] = [
  {
    start: new Date(2020, 1, 1),
    end: new Date(2020, 1, 2),
    name: 'Idea',
    id: 'Task 0',
    type: 'task',
    progress: 45,
    isDisabled: true,
    styles: { progressColor: '#ffbb54', progressSelectedColor: '#ff9e0d' },
  },
  ...
];
<Gantt tasks={tasks}/>

You may handle actions

<Gantt
  tasks={tasks}
  viewMode={view}
  onDateChange={onTaskChange}
  onTaskDelete={onTaskDelete}
  onProgressChange={onProgressChange}
  onDoubleClick={onDblClick}
  onClick={onClick}
/>

How to run example

cd ./example
npm install
npm start

Gantt Configuration

GanttProps

Parameter Name Type Description
tasks* Task An array of tasks to display in the Gantt chart.
viewMode ViewMode Specifies the time scale for the chart.
onDateChange function Callback when a task's start or end date changes.
onProgressChange function Callback when a task's progress changes.
onDoubleClick function Callback when a task is double-clicked.
onClick function Callback when a task is clicked.
rtl boolean Right-to-left display mode.
locale Locale Localization for date and time formatting.
barBackgroundColor string Background color of task bars.
barProgressColor string Color of the task bar's progress indicator.
projectBackgroundColor string Background color for project tasks.
milestoneBackgroundColor string Background color for milestone tasks.
todayColor string Color of the "today" indicator line.
arrowColor string Color of dependency arrows.
fontFamily string Font family for the chart.
fontSize string Font size for text within the chart.
rowHeight number Height of each row.
columnWidth number Width of each time unit column.
ganttHeight number Total height of the Gantt chart.
ganttWidth number Total width of the Gantt chart.
taskHeight number Height of task bars within each row.
dependencies boolean Display task dependencies as arrows.
taskListCellWidth string Width of the task list cell. Empty to hide.
dragStep number Time step for dragging actions, in milliseconds.

EventOption

Parameter Name Type Description
onSelect (task: Task, isSelected: boolean) => void Function to execute on taskbar select/unselect event.
onDoubleClick (task: Task) => void Function to execute on taskbar double-click event.
onClick (task: Task) => void Function to execute on taskbar click event.
onDelete* (task: Task) => void/boolean/Promise/Promise Function to execute on taskbar delete button press event.
onDateChange* (task: Task, children: Task[]) => void/boolean/Promise/Promise Function to execute when dragging taskbar event on timeline finishes.
onProgressChange* (task: Task, children: Task[]) => void/boolean/Promise/Promise Function to execute when dragging taskbar progress event finishes.
onExpanderClick* onExpanderClick: (task: Task) => void; Function to execute on the table expander click.
onWheel* onWheel: (wheelEvent: WheelEvent) => void; Function to execute when the mouse wheel is used.
timeStep number Time step value for onDateChange. Specify in milliseconds.

Chart undoes operation if method returns false or error. Parameter children returns one-level deep records.

DisplayOption

Parameter Name Type Description
viewMode enum Specifies the time scale. Options: Hour, Quarter Day, Half Day, Day, Week(ISO-8601, 1st day is Monday), Month, QuarterYear, Year.
viewDate date Specifies display date and time for display.
preStepsCount number Specifies empty space before the first task.
locale string Specifies the month name language. Able formats: ISO 639-2, Java Locale.
monthCalendarFormat string Specifies the month display on the calendar.
monthTaskListFormat string Specifies the month display on the list.
rtl boolean Sets rtl mode.
roundDate Allows customizing the way the date start/end are rounded.
checkIsHoliday Tells if a date is a holiday. Impacts the style of the day and the way the date is adjusted to working days.
dateMoveStep An object corresponding to a duration. Gives the step to adjust to the working day when moving the date allowing smooth feedback.

StylingOption

Parameter Name Type Description
headerHeight number Specifies the header height.
columnWidth number Specifies the time period width.
listCellWidth string Specifies the task list cell width. Empty string means "no display".
rowHeight number Specifies the task row height.
barCornerRadius number Specifies the taskbar corner rounding.
barFill number Specifies the taskbar occupation, in percent from 0 to 100.
handleWidth number Specifies the width of the taskbar drag control for start and end dates.
fontFamily string Specifies the font family for the application.
fontSize string Specifies the font size for the application.
barProgressColor string Specifies the taskbar progress fill color globally.
barProgressSelectedColor string Specifies the taskbar progress fill color globally when selected.
barBackgroundColor string Specifies the taskbar background fill color globally.
barBackgroundSelectedColor string Specifies the taskbar background fill color globally when selected.
arrowColor string Specifies the relationship arrow fill color.
arrowIndent number Specifies the relationship arrow right indent, in px.
todayColor string Specifies the current period column fill color.
TooltipContent React.FC<{ task: Task; fontSize: string; fontFamily: string; }>; Specifies the Tooltip view for selected taskbar.
TaskListHeader React.FC<{ headerHeight: number; rowWidth: string; fontFamily: string; fontSize: string;}>; Specifies the task list Header view
TaskListTable React.FC<{ rowHeight: number; rowWidth: string; fontFamily: string; fontSize: string; locale: string; tasks: Task[]; selectedTaskId: string; setSelectedTask: (taskId: string) => void; }>; Specifies the task list Table view

Task

Parameter Name Type Description
id* string Task id.
name* string Task display name.
type* string Task display type: task, milestone, project
start* Date Task start date.
end* Date Task end date.
progress* number Task progress. Sets in percent from 0 to 100.
assignees* string[] List of people assigned to the task
dependencies string[] Specifies the parent dependencies ids.
styles object Specifies the taskbar styling settings locally. Object is passed with the following attributes:
- backgroundColor: String. Specifies the taskbar background fill color locally.
- backgroundSelectedColor: String. Specifies the taskbar background fill color locally on select.
- progressColor: String. Specifies the taskbar progress fill color locally.
- progressSelectedColor: String. Specifies the taskbar progress fill color globally on select.
isDisabled bool Disables all action for current task.
fontSize string Specifies the taskbar font size locally.
project string Task project name
hideChildren bool Hide children items. Parameter works with project type only

*Required

License

MIT